Project Overview
This case study focuses on the South Ashford Garden Community (SAGC) project, a housing-led urban extension encompassing three former greenfield sites, where a mix of landowners and development partners are working with local communities to retroactively shape a holistic vision and strategy for a new community south of Ashford in Kent. It reflects on how principles of co-production and co-design can be integrated in masterplanning at an early stage before physical design, and how community-led stewardship structures can be set up to deliver a high-quality garden community.
Core Project Structures & Activities
1. Design Code & Quality Charter
A charter was co-produced through public consultation and charettes. The charter sets out a benchmark for design quality through 36 commitments across all facets of the development – such as ensuring that every home will receive a fruit tree in its back garden. All of the developers, the Local Authority and the County Council signed their names to this document.
2. Non-profit Stewardship Organisation: Chilmington Management Organisation
The CMO was set up as a socially-minded, community-led organisation that would take a proactive approach to community asset management and long-term development. This is a hybrid model which operates like a traditional land management company but is led by its membership – the residents of Chilmington.
3. Community Stakeholder Group
To ensure that the Delivery & Implementation Board is responding to the concerns of local people, a pre-existing Community Stakeholder Group was asked to meet bi-monthly with the Head of Planning and lead developer. This group, comprising residents in and around rural Chilmington Green, had built a strong understanding of planning matters, having been through significant consultation on previous Local Plans and an earlier policy framework from which the development had emerged.
4. Project team
Known as the Chilmington Project Team, a team of three at Ashford Borough Council were responsible for the programme management and governance at Chilmington, operating the CMO through a service agreement and coordinating the SAGC until the CMO received enough funding to self-operate.
5. Meanwhile projects
An artist-in-residence led a project about local heritage with existing community members around Chilmington. The artist spent two months building relationships, running school workshops and developing a final output which was co-produced by members of the local Repair Café. This contributed to establishing stronger local ties, providing direction for the community development and the branding of the Garden Village.